EAST KOWLOON CULTURAL CENTRE

STATUS: CURRENT PROJECT

SERVICES:

RC FRAME CONTRACTOR

-  BASEMENT FOUNDATIONS

-  RC STAIRCASES

-  SUB & SUPERSTRUCTURE

-  BASEMENT WATERPROOFING

CLIENT:

LEIGHTON CONTRACTORS​​ (ASIA) LIMITED

PROJECT DESCRIPTION:

The centre will house performance halls including a 1,200-seat multi-purpose hall and a 550-seat theatre.

PROJECT HIGHLIGHTS (TO DATE):

2019 SEP - Mid-autumn festival Briefings & Festivities with Clients/ Main contractors & Sub contractors

2019 JAN-FEB - TGL poured over 2000m³ of concrete every week on superstructure columns and floors

2018 JUN - Basement sub-structure completion milestone

2017 DEC - First site pour on 23rd December - celebrated with a “bai-sun”(worship) ceremony to mark the occasion

2016 AUG - Site enabling works marks commencement of project